Tembusu Multi Utilities Complex (TMUC) Jetty
Jurong Island, Singapore
The first EPC project for HSL, Tembusu Multi Utilities Complex (TMUC) Jetty project has became another stepping stone for us to become the leading solution provider in engineering, construction and project management.
Even going into the project fully aware that it would be highly challenging and restricted by a tight budget, we were committed to deliver a quality product, on time, and with zero harm. The vast scope of works included piling, dredging and shore revetment, construction of jetty head, mechanical and electrical works. Using a modular precast concrete deck enhanced productivity at the site and an innovative silt curtain contributed cost savings to the project.
Through hard work and dedication, we gained the client’s trust which helped us secure additional works, thus increasing our revenue. We have committed to hand over the project ahead of schedule and are confident that its quality would exceed expectations.
Client
- Tuas Power
Location
- Jurong Island, Singapore