Naphtha Import Facilities

Jurong Island, Singapore

Scope: EPC of Tank Farm with Import Berth Facilities

  • Berth Facilities for 120,000 DWT
  • Firewater Pump House
  • 8 No. of Tanks with Geodesic and Internal Floating Roof (30,000 m3 Each)
  • Interconnecting Pipelines (100,000 Dia Inch)
  • Substation and Storage Building
  • E& I Works
  • Steel Structure
  • Equipment (Pumps, Loading Arms, etc)
  • External Works, Drainage, Roads

Construction method video may be viewed here.

Client

  • Petrochemical Corporation of Singapore (PCS)

Period

  • December 2015 - September 2017
  • (21 months)